Nanaimo, City of

South Fork Dam, Intake Pipe and Tunnel Lining

Finished Project

Pipe Finished


Out Take Pipe Finished

Out Take Pipe Finished

Out Take Before

Out Take Before

Value: $250,000
Material: Lacquer Thinner, Barrust 236, Barrust 233, T-10 thinner
Amounts: Barrust 236 – 58 gal, Thinner T-10 – 10 gal, Barrust 233 – 3 gal
Equipment: Holding tanks, scaffold, Roto-peen hammer, Desiccant Dehumidifier, 5000 PSI Pressure Washer, Drivet gun, 55 KW Generator, Submersible Pump, 185 CFM Compressor, 320,000 BTU Heater, Explosion Proof lights, King pump
No of Employees: 8
Special Safety: Harnesses and Lanyards required at all times. P.P.E.
Duration: Oct 10, 2005 – Nov 20, 2005