Spectra Energy Transmission

Pipeline Pier Crossing Painting


Finished Project

Finished Project

Value: $150,000
Material: Devthane 379, Cathacoat 302H, Thinner T-10, Barrust 236, Thinner T-9, Sil7 Sand
Amounts: Devthane 379 – 26 gal, Cathacoat 302H – 35 gal, Thinner T-10 – 15 gal, Barrust 236 – 75 gal, Thinner T-9 – 5 gal, Sil7 sand – 56,217 lbs
Equipment: 6 ton Blast rig with HIAB, 60’ manlift, 750 CFM compressor, 56:1 Airless Spay pump
No of Employees: 3
Special Safety: Fall protection, equipment containment. Spill kits, fire extinguishers, eye wash stations, respirators.
Duration: Sept 4, 2007 – Sept 25, 2007