Mainroad Contracting Ltd.

Bridge Expansion Joint Trough Replacement

Value: $100,000
Material: Kleen Blast, Carbothane, Carbomastic, Thinner 10, Thinner T25
Amounts: Kleen Blast – 3280 lb, Thinner T 25 – 3 gal, Thinner 10 – 2 gal, Carbothane 134 – 6 gal, Carbomastic – 6 gal
Equipment: 375 CFM compressor and air dryer, 3 KW Generator, 3500 PSI Pressure Washer, 600 lb blast pot.
No of Employees: 4
Special Safety: Traffic control, rolling containment.
Duration: Sept 5, 2006 – June 4, 2007