British Columbia Ferry Services Inc.
Refurbish pontoon containment piles, apron, and ramp lifting beam

Finished Ramp

Under Ramp
| Value: | $200,000 |
|---|---|
| Material: | Interseal 670HS, Interzone 954, Thinner GTA45, Interzinc 52, MEK, Kleen Blast Abrasive |
| Amounts: | Interseal 670HS – 96 gal, Interzone 954 – 65 gal, Thinner GTA45 – 30 gal, Interzinc 52 – 28 gal, Kleen Blast – 62,000 lbs, MEK – 3 gal |
| Equipment: | Generator, 185 and 850 cfm compressors and air dryers, 6 ton blast pot, 320,000 BTU Indirect Heater, Needle guns, Forklift, 24,000 CFM Dust collector, 45:1 and 56:1 airless spray pump |
| Number of Employees | 6 |
| Special Safety: | Scaffold and tarp containment, fall protection, rescue boat, life preservers. Spill kits, fire extinguishers, eye wash stations, respirators. |
| Duration: | October 23, 2006 – Oct 11, 2007 |