BC Hydro
AB, Service and Radial Gates, removal of coal tar epoxy, welding repair, Application of new epoxy coating and moisture cure polyurethane caulking
| Value: | $50,000 |
|---|---|
| Material: | Barrust 236,T-10 thinner, KleenBlast |
| Amounts: | 101 Gal Barrust 236, 15 gal 5-10 Thinner, 19,400 lbs KleenBlast 16/30 |
| Equipment: | 10 ton Forklift, 15 Ton Crane, Welder, 80 & 50 hp electric compressor, 600 lb blast pot, 56:1 airless Spray pump, rolling scaffold |
| No of Employees: | 3 |
| Special Safety: | Fabrication of large support arms to stabilize gates in vertical position. MST supplied breathing air, ventilation system |
| Duration: | November 4, 2003 – March 31, 2004 |